This project was competitively tendered over Christmas 2007 and with a return date of 27th December 2007. The Contract was awarded on the 2nd January 2008 with an immediate start.

Click on the slide!

Billericay Police Station

Case Studies >> CG Interiors

Project Name

Billericay Police Station was converted by CG Interiors to conform to the Disability Discrimination Act. We removed the existing ramp, front entrance steps, entrance doors and public counter. We converted the existing office, formed a new disabled toilet facility along with other internal office alterations to assist disabled persons accessibility.

Click on the slide!

Mayflower

Case Studies >> CG Interiors

Project Name

This project was to construct an extension to the school to allow for the installation of a new lift. The scope included construction of a new entrance ramp and canopy, alterations to the ground, first and second floor classrooms and refurbishment of existing toilet facilities.

Click on the slide!

38 Finsbury Square

Case Studies >> CG Interiors

Project Name

CG Interiors were originally commissioned to carry out the soft strip demolitions and builders work on the existing building. Additional work packages included: - roofing, flooring, new internal block work walls, suspended ceilings, plastering, painting and decorating, structural openings for a new lift installation and new services including the renewal of major plant on the roof were also undertaken.

Click on the slide!

857 London Road

Case Studies >> CG Interiors

Project Name

This waste land site was acquired in July 2007 with the possibility of planning a new build office and warehouse construction. We assisted the clients in obtaining planning permission and with appointment of the lead architect.

Frontpage Slideshow (version 2.0.0) - Copyright © 2006-2008 by JoomlaWorks
Enfield DDA

1
Brief Description:The works were all tendered on the basis of mini competition and awarded to CG to carry out over the last year.

We have previously developed a partnership approach to working with LBE and provided a high level of service, not only on planned projects but also reactive.

Our experienced team of DDA specialists work closely with the borough to provide design and installation services across a spectrum of housing stock and public buildings.

3
Design & Innovation: Planning and design of each space is critical and different for each property and ultimately each resident.

Our management have had 7 years experience with DDA improvements and regulation and have provided a key role in developing this area of our business.

Knowledge of the latest products and how these can be integrated for improvement in life cycle maintenance has been a key driver for LBE and CG in the partnership.

5
7
Client: Enfield Council
Client Contact: Brian Gormley
Consultant: Various
Project: Disabled Adaptations for various properties in Enfield.
Works: DDA Works to Housing Stock.
Contract Duration: 52 weeks
Contract Sum: £850,000
2
The Programme:The projects are all individually programmed but most properties are normally converted within 7 days.

Major refurbishments incorporating kitchens and stair lifts have taken up to 10 weeks.

All works are carried out in full occupation working around the residents with minimal inconvenience and maintenance of services.

4
6
What Our Clients Say: "Great contractor, great team of guys and very good at what they do!"- Brian Gormley LBE

"I would just like to thank CG so much for the difference their works have made to me and my life, Thankyou"- Resident

 

Essex Office

857 London Road
West Thurrock
Grays
Essex
RM20 3AT

Map & Directions

Sheffield Office

Unit 19
85 Leigh St Ind Est
Sheffield
S9 2PR

Map & Directions

Contact Details

Tel: 0845 873 8833
Fax: 0845 873 8834
Email: sales@cg-group.co.uk

outperformance as standard

Cre8ive Imagery

Disclaimer

Whilst the CG Group of companies, including Cranegates Limited and CG Interiors Ltd make every effort to keep the information on this web-site accurate, they disclaim any warranty or representation, express or implied about its accuracy, completeness or appropriateness for particular purpose.

Thus, you assume full responsibility for using the information on this web-site, and you understand and agree that neither the CG Group nor any of their employees are responsible or liable for any claim, loss or damage resulting from its use.

Privacy Policy

We operate in accordance with the 1998 Data protection act in respect of any personal information you may supply, e.g. name, address, e-mail, etc.. We will not sell or supply any information you provide to third parties. If you are a user with general public and anonymous access, the CG Group Web Site (www.cg-group.co.uk) does not store or capture personal information, but merely logs your IP address which is automatically recognised by the web server. This statement only covers the CG Group Web Site maintained by CG Group. This statement does not cover other websites linked to from within this site. The system will record your e-mail address and other information if volunteered to us by you. This shall be treated as proprietary and confidential and will only be used to provide the services you have specifically signed up for. By subscribing to these services, you are giving your consent to CG Group to hold this information.

{component}option=com_xmap&sitemap=1&Itemid=22{/component}