| Guys Roman Suite |
|
Brief Description:This project was competitively tendered over Christmas 2007 and with a return date of 27th December 2007. The Contract was awarded on the 2nd January 2008 with an immediate start.
The priority was to get the function suite completed in readiness for various events that were programmed. The Works involved the complete strip out within the live hospital and new fit out of all services, rewiring, new ceilings and all new finishes including a specialist contractors design acoustic controlled lighting installation using state of the art LED's. Design & Innovation: The designer was critical to the aesthetics and finishes in the project and CG provided assistance with integration of acoustic lighting and the use of colour changing up lighters to display the wall surfaces.
The lighting was linked to the music interface so the room could be used for multipurpose activities. The carpet was a bespoke weave which we assisted the client in obtaining as a one-off design. The wall images were chosen by the architect and integrated using Muraspec vinyl image wall coverings. Client: Guys & St Thomas’ NHS Trust
Client Contact: Allen Watling (Facilities and Estates) Consultant: Monument design - Derek Rainbow Project: Roman Suite, 29th Floor, Guys Hospital Works: Complete fit out of 29th floor to convert into a function suite Contract Duration: 8 weeks Contract Sum: £175,000 The Programme:The work commenced the first week back after Christmas with no lead in period and within a live hospital building.
Careful planning and out of hours working were critical to this projects success working around the occupants. The contract period was 8 weeks and completed on time. What Our Clients Say: "Another great job by CG under very tight timescales and difficult working conditions" - Allen Watling- Estates Manager
"We are extremely pleased with the facility and it is proving a huge success for the hospital and makes a great venue for events"- Events Manager |