| Portman Estates Cyclical A |
|
Brief Description:The works included roof repairs, stone renovation, brickwork stitching and re-pointing, redecorations and woodcare repairs to sash windows.
The area of works was around Marble Arch in London and is a very exclusive area with private tenure to all properties leased by the estate. Particular attention was focused on RLO duties and liaison with residents and occupied businesses, to ensure communications was paramount and assist in the success of the project Design & Innovation: All scaffolding had to be erected up and over from the front elevation to each rear elevation. The rear elevations contained extensions and additional buildings so access methods were key to this project.
We pre-surveyed all properties to ensure that a system scaffold could be used to the rear elevations wherever possible and utilised hanging scaffold and cradles to minimise the impact on residents. Client: Portman Estates
Client Contact: Mark Davies Consultant: Frankham Consultancy Services Project: Cyclical repairs & redecorations Phase 1 Works: Complete external repairs and redecorations Contract Duration: 12 weeks Contract Sum: £212,000 The Programme:The project commenced in February 2007 and completed in April 2007.
The main time related issues with this project surrounded the roll on of scaffolding and trades from property to property, ensuring there was no compromise on programme or delay to our client. What Our Clients Say: "It was a breath of fresh air to have worked with CG on this project."
"Not only did they complete on time but unlike other contracts we received no complaints during this project and the standard of work was very good." |