| Winkfield Resource Centre |
|
Brief Description: We were appointed by LB Haringey to carry out the complete refurbishment and fire reinstatement following a vicious arson attack at the Winkfield Resources Centre.
The roof structure was completely destroyed by the fire which created many issues in terms of the stability of the structure and hazards in working. All the finishes and mechanical/electrical installations were also completely damaged. The roof was hand crafted and had to be remade to replicate the existing design in its entirety; our own craftsmen spent 2 weeks on site remaking all the components by hand to produce identical results. Design, Health & Safety: We are pleased to say that despite the hazardous conditions left by the fire, our works were completed accident free and safe methods were utilised to overcome the risks involved here.
Our operatives worked extremely hard in the construction of this project in particular with the handmade rafters. Due to the installation of a moveable wall the main hall space can now be utilised for a number of different functions. Client: Haringey Council
Client Contact: Mike Healy Consultant: Frankham Consultancy Services Project: Winkfield Resources Centre Works: Fire reinstatement and refurbishment works Contract Duration: 18 weeks Contract Sum: £124,995 The Programme: Works commenced in November 2006 and completed in April 2007.
There were no major issues to the programme other than the weather through the winter and constructing the handmade rafters on site. The centre was back open for business in summer 2007 and continues to use the multi function facility for a number of events. What Our Clients Say: "We would like to say a big thank you to Barry, Mark and all at CG
for their efforts in this project. It’s good to work with good contractors that have pride in their work and a flexible approach to challenges." |