Click on the slide!

Guys Roman Suite

Case Studies >> CG Interiors

This project was competitively tendered over Christmas 2007 and with a return date of 27th December 2007. The Contract was awarded on the 2nd January 2008 with an immediate start.

Click on the slide!

857 London Road

Case Studies >> CG Interiors

Project Name

This waste land site was acquired in July 2007 with the possibility of planning a new build office and warehouse construction. We assisted the clients in obtaining planning permission and with appointment of the lead architect.

Click on the slide!

Mayflower

Case Studies >> CG Interiors

Project Name

This project was to construct an extension to the school to allow for the installation of a new lift. The scope included construction of a new entrance ramp and canopy, alterations to the ground, first and second floor classrooms and refurbishment of existing toilet facilities.

Click on the slide!

38 Finsbury Square

Case Studies >> CG Interiors

Project Name

CG Interiors were originally commissioned to carry out the soft strip demolitions and builders work on the existing building. Additional work packages included: - roofing, flooring, new internal block work walls, suspended ceilings, plastering, painting and decorating, structural openings for a new lift installation and new services including the renewal of major plant on the roof were also undertaken.

Click on the slide!

Billericay Police Station

Case Studies >> CG Interiors

Project Name

Billericay Police Station was converted by CG Interiors to conform to the Disability Discrimination Act. We removed the existing ramp, front entrance steps, entrance doors and public counter. We converted the existing office, formed a new disabled toilet facility along with other internal office alterations to assist disabled persons accessibility.

Frontpage Slideshow (version 2.0.0) - Copyright © 2006-2008 by JoomlaWorks
Hospitals
1
Client: Wallis
Client Contact: Jenny Hong
Project: Guys Hospital Tower
Works: Asbestos removal
Contract Duration: 14 weeks
Contract Sum: £170,000
Brief Description: This was a sensitive project for the trust as it involved working near Aspergillum fungus sufferers who are susceptible to dusty environments.

As a combined project Cranegates Ltd carried out the asbestos removal over 3 floors, removing ceilings, floor tiles and flues, whilst CG Interiors provided logistics and carried out the soft strip of all walls, ceilings, partition walls etc. and completed the builders works.

During the building works we used a local exhaust system, fitted with an adapted hepa filter giving 99.9% filtration thus preventing heavy airborne dust particles.
3
Client: Real Time Civil Engineering
Client Contact: Mark Comiskey
Project: Springfield Hospital
Works: Removal of Asbestos Insulation from pipe services
Contract Duration: 6 weeks
Contract Sum: £394,000
Brief Description:The works at Springfield Hospital consisted of the removal of insulation from pipe services concealed within service ducts running throughout the grounds of the hospital.

All works were carried out under fully controlled conditions including the exposure of the service duct by removing the concrete slab and sub-soil. All the asbestos works were carried out to a very tight program as failure to complete on time would have prevented the start of a 70 million pound new build scheme.
2
Client: Gleeson Homes
Client Contact: Mark Davis
Project: Netherne Hospital
Works: Asbestos removal
Contract Duration: 12 weeks
Contract Sum: £1,000,000
Brief Description: Built in 1905 Netherne Hospital was one of the largest asylums in the south east. As part of the regeneration of the area Gleeson Homes demolished parts of the hospital to form Netherne on the Hill Village.

Cranegates Ltd was employed to remove all of the asbestos from service tunnels, service ducts, corridors, wards, boiler houses, satellite buildings and roof voids. Using a team of 20 operatives we progressed around the site until all had been removed.

Following the removal Cranegates Ltd carried out a lot of the soft strip and enabling works for Gleeson, and was perhaps the first time we thought about diversifying into a builder’s work package as CG Interiors.
4
Client: Jarvis Construction
Client Contact: Jarvis Construction
Project: The Whittington Hospital
Works: Asbestos Removal / Soft strip demolition
Contract Duration: 12 weeks
Contract Sum: £150,000
Brief Description: The works consisted of the removal of asbestos insulation board and pipe insulation from various plant rooms, service ducts, the A&E escalator, and lobbies. Soft strip demolition of Blocks L and K including removal of high level link bridge between buildings, the works were carried out whilst the building remained fully functional. These works were part of a major refurbishment and new build of the A&E Department carried out by Jarvis. We were also employed to carry out the soft strip demolitions of blocks K and C.
 

Essex Office

857 London Road
West Thurrock
Grays
Essex
RM20 3AT

Map & Directions

Sheffield Office

Unit 19
85 Leigh St Ind Est
Sheffield
S9 2PR

Map & Directions

Contact Details

Tel: 0845 873 8833
Fax: 0845 873 8834
Email: sales@cg-group.co.uk

outperformance as standard

Cre8ive Imagery

Disclaimer

Whilst the CG Group of companies, including Cranegates Limited and CG Interiors Ltd make every effort to keep the information on this web-site accurate, they disclaim any warranty or representation, express or implied about its accuracy, completeness or appropriateness for particular purpose.

Thus, you assume full responsibility for using the information on this web-site, and you understand and agree that neither the CG Group nor any of their employees are responsible or liable for any claim, loss or damage resulting from its use.

Privacy Policy

We operate in accordance with the 1998 Data protection act in respect of any personal information you may supply, e.g. name, address, e-mail, etc.. We will not sell or supply any information you provide to third parties. If you are a user with general public and anonymous access, the CG Group Web Site (www.cg-group.co.uk) does not store or capture personal information, but merely logs your IP address which is automatically recognised by the web server. This statement only covers the CG Group Web Site maintained by CG Group. This statement does not cover other websites linked to from within this site. The system will record your e-mail address and other information if volunteered to us by you. This shall be treated as proprietary and confidential and will only be used to provide the services you have specifically signed up for. By subscribing to these services, you are giving your consent to CG Group to hold this information.

{component}option=com_xmap&sitemap=1&Itemid=22{/component}