Click on the slide!

Billericay Police Station

Case Studies >> CG Interiors

Project Name

Billericay Police Station was converted by CG Interiors to conform to the Disability Discrimination Act. We removed the existing ramp, front entrance steps, entrance doors and public counter. We converted the existing office, formed a new disabled toilet facility along with other internal office alterations to assist disabled persons accessibility.

Click on the slide!

Mayflower

Case Studies >> CG Interiors

Project Name

This project was to construct an extension to the school to allow for the installation of a new lift. The scope included construction of a new entrance ramp and canopy, alterations to the ground, first and second floor classrooms and refurbishment of existing toilet facilities.

Click on the slide!

38 Finsbury Square

Case Studies >> CG Interiors

Project Name

CG Interiors were originally commissioned to carry out the soft strip demolitions and builders work on the existing building. Additional work packages included: - roofing, flooring, new internal block work walls, suspended ceilings, plastering, painting and decorating, structural openings for a new lift installation and new services including the renewal of major plant on the roof were also undertaken.

Click on the slide!

857 London Road

Case Studies >> CG Interiors

Project Name

This waste land site was acquired in July 2007 with the possibility of planning a new build office and warehouse construction. We assisted the clients in obtaining planning permission and with appointment of the lead architect.

Click on the slide!

Guys Roman Suite

Case Studies >> CG Interiors

This project was competitively tendered over Christmas 2007 and with a return date of 27th December 2007. The Contract was awarded on the 2nd January 2008 with an immediate start.

Frontpage Slideshow (version 2.0.0) - Copyright © 2006-2008 by JoomlaWorks
Landmarks
1
Client: Schmidlin UK
Client Contact: Paul Haslam
Project: Nat West Tower
Works: Removal of AIB
Contract Duration: 26 weeks
Contract Sum: £260,000
Brief Description:Each window mullion was lined with Asbestos insulation board, which had become disturbed following a terrorist bomb strike.

The project required us to remove every window and mullion, and then strip the Asbestos from the mullion in a remote location. The works had to be carried out using a unique access cradle system which was erected on the roof level then lowered down the outside of the building on pulleys. The new windows were then installed on the above tier of the 3 tier cradle which meant there was always someone working immediately above us which made safety a major issue.
3
Client: Pinewood Studios Group
Client Contact: Darren Teverson
Project: Pinewood Studio
Works: Removal of corrugated asbestos cement roof sheets
Contract Duration: 3 weeks
Contract Sum: £27,500
Brief Description: Cranegates Ltd were employed directly by possibly the most famous film studio in the world. Our contract was to remove the original corrugated wall cladding, this was to facilitate a major upgrade of the roof and curtain walling.

Our operatives, fully trained in the use of mobile elevation platforms, gained access to the roof and walls.

Enabling us to carefully release and remove the a/c sheets to the floor. Where they were wrap/sealed and placed in our disposal container. The structure was then fine cleaned and prepared ready for the new applications.
2
Client: Bovis
Client Contact: Jon Conway
Project: Former London Stock Exchange
Works: Removal of inner flue lining and asbestos block
Contract Duration: 16 weeks
Contract Sum: £440,000
Brief Description: The works entailed the removal of the inner concrete flue lining sections and asbestos lining blocks from the basement to the 28th floor and roof level with no easy means of access.

At every floor level we erected a scaffold platform to allow emergency egress from the flue and to allow waste removal.

Unfortunately this was not sufficient to allow us to work in the flue; we therefore had to engineer another option to get the asbestos liner out. It was at this point we designed a two person boson hoist which was lowered from the roof inside the flue to the ground floor, some 260’ in all.
4
Client: Trafalgar House (Skanska)
Client Contact: Gary Clifford
Project: Bank of England Printing Works
Works: Removal of Asbestos works throughout the Printing Works
Contract Duration: 1 year
Contract Sum: £1.5 million
Brief Description: Cranegates Ltd was involved in the major refurbishment of the Bank of England printing works from start to finish. As an existing contractor already working at the printing works we were able to bring a lot of knowledge to the design table and assist our client – Trafalgar House.

The site is security sensitive for obvious reasons and meant all operatives had to pass stringent security checks before being allowed in. The logistics of the project proved difficult in many areas as the printing works was in full production at all times, this was definitely the case when asbestos was discovered in the concrete roof structure during the window replacement above them main print floor. The asbestos had been cast as fixing blocks to prevent drilling into the beams and was only discovered during the window removal, this was stopped and Cranegates Ltd erected full enclosures over the main print hall and removed all the windows from a birdcage scaffold.
 

Essex Office

857 London Road
West Thurrock
Grays
Essex
RM20 3AT

Map & Directions

Sheffield Office

Unit 19
85 Leigh St Ind Est
Sheffield
S9 2PR

Map & Directions

Contact Details

Tel: 0845 873 8833
Fax: 0845 873 8834
Email: sales@cg-group.co.uk

outperformance as standard

Cre8ive Imagery

Disclaimer

Whilst the CG Group of companies, including Cranegates Limited and CG Interiors Ltd make every effort to keep the information on this web-site accurate, they disclaim any warranty or representation, express or implied about its accuracy, completeness or appropriateness for particular purpose.

Thus, you assume full responsibility for using the information on this web-site, and you understand and agree that neither the CG Group nor any of their employees are responsible or liable for any claim, loss or damage resulting from its use.

Privacy Policy

We operate in accordance with the 1998 Data protection act in respect of any personal information you may supply, e.g. name, address, e-mail, etc.. We will not sell or supply any information you provide to third parties. If you are a user with general public and anonymous access, the CG Group Web Site (www.cg-group.co.uk) does not store or capture personal information, but merely logs your IP address which is automatically recognised by the web server. This statement only covers the CG Group Web Site maintained by CG Group. This statement does not cover other websites linked to from within this site. The system will record your e-mail address and other information if volunteered to us by you. This shall be treated as proprietary and confidential and will only be used to provide the services you have specifically signed up for. By subscribing to these services, you are giving your consent to CG Group to hold this information.

{component}option=com_xmap&sitemap=1&Itemid=22{/component}